Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed

Clearbakk Rockyview
Stats
-
Zero lost time injuries
-
Project delivered ahead of schedule and on budget
Module Assembly
-
Over 700 LM of piping, majority 304L stainless
-
Pump alignments and strain checks
-
Coordination and interface planning with numerous subcontractors (electrical, structural, building contractors)
-
Over 30 pressure vessels and 24 pumps
1/16