top of page
Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed

PROJECTS
Sem Cams Wapiti
Gas Plant
200 MMscfd
Keyera Pipestone
Sour Compressor Station
90 MMscfd
SemCAMS
SemCAMS 200 mmscf Wapati Gas Plant
SemCAMS
SemCAMS 200 mmscf Wapati Gas Plant
1/1
Keyera
Keyera Pipestone Sour Gas Station
Keyera
Keyera Pipestone Sour Gas Station
1/1
Connacher Fort McMurray
Heavy Oil (SAGD)
41 Well Pairs, 15,000 BPD
Connacher Oil & Gas
Fort McMurray, the Great Divide and Algar
Connacher Oil & Gas
Fort McMurray, the Great Divide and Algar
Connacher Oil & Gas
Fort McMurray, the Great Divide and Algar
Connacher Oil & Gas
Fort McMurray, the Great Divide and Algar
1/3
Keyera Fort Saskatchewan
NGL Processing Facility
Overall Capacity 65,000 BPD
Fort Saskatchewan Gas Plant - Keyera
Fort Saskatchewan Gas Plant - Keyera
Fort Saskatchewan Gas Plant - Keyera
1/2
Sunshine West Ells
Heavy Oil (SAGD)
5,000 BPD

Clearbakk - Suncor
Heavy Oil (SAGD)

Pembina Lator
Gas Plant
2,500 m³ C2+ liquids storage c/w two 450 HP pumps

Keyera FSCS
Condensate Manifold
600,000 BPD

Keyera Ft. Saskatchewan
Tie Ins

Lafarge Exshaw
Mining / Industrial
Exshaw Cement Plant - Lafarge 2016
Exshaw Cement Plant - Lafarge 2016
Exshaw Cement Plant Lafarge 2016 (2)
Exshaw Cement Plant - Lafarge 2016
1/3
Keyera Simonette
Gas Plant
100 MMscfd, 5,000 BPD Condensate

Enbridge Hardisty
Pump Station
4 - 3,000 HP Pumps

Laricina Wabasca
Heavy Oil (SAGD)
5,000 BPD

Plains Fort Saskatchewan
NGL Processing

Pembina Resthaven
Gas Plant
300 MMscfd

Conoco Wembley
Shutdown