Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed

Enbridge
Hardisty
Stats
-
Zero lost time injuries
-
2% weld repair rate on CSA 483 piping material
-
Project delivered ahead of schedule and on budget
-
Maintained a 25% aboriginal involvement, indenturing 3 new apprentices and mentor-ships
Field Mechanical Construction
-
Large bore CSA Gr. 483 high tensile (24", 36" and 42")
-
200 TNE of structural steel installed
-
6,800 diameter inches fabricated
-
Full on site, system hydrotest
-
Pump strains on 4-3000 Hp pumps (24" sch. 80 lines). all passed 0.002" deflection without cut outs or re-welding