Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed

Keyera
Ft. Saskatchewan
Stats
-
Zero Lost Time Injuries
-
Peak manpower – 55 day shift and 25 craft labour night shift
-
1 - project on time and schedule
-
Project executed 2% below budget
Field Mechanical Construction
-
Management of Change and Expansion Projects
-
C3 Frac Tie in project
-
96 tie ins total
-
14 underground firewater and pentane lines
-
24 live lines requiring scheduled outages
-
58 during plant shut down