Keyera
Ft. Saskatchewan
Stats
-
Zero Lost Time Injuries
-
Peak manpower – 55 day shift and 25 craft labour night shift
-
1 - project on time and schedule
-
Project executed 2% below budget
Field Mechanical Construction
-
Management of Change and Expansion Projects
-
C3 Frac Tie in project
-
96 tie ins total
-
14 underground firewater and pentane lines
-
24 live lines requiring scheduled outages
-
58 during plant shut down