Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed

Keyera FSCS
Stats
-
Zero Lost Time Injuries
-
7,700 Diameter inches of CSA 483 pipe (16", 24", 36")
Field Mechanical Construction
-
Winter work conditions
-
On site fabrication
-
On site hydro test (125 m³)
-
Condensate manifold pigging facilities and metering skids
Click to Expand