Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed

Keyera Ft. Saskatchewan
Stats
-
C3+ Frac Tie in project consisting of 96 tie ins: 14 underground (C5+, butane, firewater, propane, brine, FG, etc.)
-
Management of subcontractors including: earthworks, NDE, PWHT, Insulators and E&I
-
24 live requiring scheduled outages various gas, condensate, process and 58 to be tied in during plant shutdown.
-
Project finishing 2% below budget. Responsible for proposing and implementing a night shift (peak of 55 man crew day shift, 25 on nights) which decreased the duration of the shutdown from 8 days to 5.