Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed

Laricina
Wabasca
Stats
-
Project completed on budget
-
Setting and installation of major equipment (Tanks, Packages, Vessels ect.)
-
Setting and installation of building and pipe rack modules
-
Structural steel and interconnecting piping
-
Quality control and turnover
-
Glycol tree installation and hydrotesting