Pembina Lator
Stats
-
Radium was the prime contractor
-
Zero lost time injuries
-
4 LACT modules
-
10,000 DI's of piping fabrication
-
50 tonnes of structural steel
Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed
Stats
Radium was the prime contractor
Zero lost time injuries
4 LACT modules
10,000 DI's of piping fabrication
50 tonnes of structural steel