Keyera
Pipestone
Stats
-
Zero lost time incidents
-
Shortened schedule by 1.5 months at client request
-
Finished 7% under budget
Field Mechanical Construction
-
Setting and installation of major equipment (tanks, packages vessels etc.)
-
Setting and installation of building and piperack modules and interconnecting piping
-
Quality control and turnover
-
Commissioning of lines not completed by a previous contractor
-
Fabricate and install 50 Tonnes of structural steel, 20,000 diameter inches
-
Cut and cap
Shop Responsibilities
-
Fabrication of 4 pipe rack modules including 100 tones of steel and 15,000 diameter inches
-
Fabrication of 4 pump buildings including 8000 Diameter inches of Piping, Electrical, Insulation, Building and Millwright work
-
67,000 Man hours