Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed

Plains
Fort Saskatchewan
Stats
-
Zero lost time incidents
-
Peak manpower - 85 craft labor & indirects
-
Project delivered ahead of schedule and under budget
Field Mechanical Construction
-
20,000 pipe inches completed including interconnects
-
50 concrete piles
-
20 tonnes of field platforms & misc. structural steel
-
2 modules
-
4 km of piping in an existing facility