Pump Stations & Compressor Stations
Sour Pump Station
-
Zero lost time incidents
-
On time and budget, working within the schedule to get the job done fast and safe.
-
Setting & installation of major equipment (tanks, package vessels)
-
Setting & Installation of building and pipe rack modules and interconnecting piping
-
quality control and turnover
-
commissioning of lines not completed by a previous contractor
-
Fabricate and install 50 tonnes of structural steel, 20,000 diameter inches.
-
Cut & cap
-
Shop Responsibilities
-
Electrical & Insulation
Pump Stations
-
Zero lost time injuries
-
Projects often delivered ahead of schedule
-
On budget
-
One of our Pump Stations we built was in a largely populated Aboriginal area. In which we Maintained a 25% aboriginal involvement, indenturing 3 new apprentices and mentor-ships.
-
Install of structural steel
-
Fabrication
-
Full on site, system hydro-test

Keyera Pipestone Sour Gas Station

Keyera Pipestone Sour Gas Station

Line 3 Hardisty Pump Station & Tie Ins

Line 3 Hardisty Pump Station & Tie Ins

Line 3 Hardisty Pump Station & Tie Ins

Line 3 Hardisty Pump Station & Tie Ins
CNRL Albian
CNRL Albian EDP Pond Piping System
-
Sr. Project Manager and Lead Estimator
-
($2.5 MM, 2 months) - 2022
-
Demo (20”), Fabrication and installation of piping (8” preinsulated) and structural steel for Inpit Tailings pond for ongoing production at MRM (including earthworks, HDPE fusing, CS welding, and testing).
​
CNRL Albian 14A Pumphouse (350-BX-101)
-
Sr. Project Manager and Lead Estimator
-
($2.5 MM, 4 months) - 2022
-
2 – 4000 Hp Slurry Pumps – Install, epoxy grouting, alignments and pipe strains
-
Large bore 28” , internally coated pipe including field measure
-
59 TNE structural fabrication and install. 300 LM piping
-
HDPE Underground Glandwater and Drain Lines
-
EHT and Insulation
-
Outage and tie ins
​
CNRL Albian HVAC Upgrades
-
Sr. Project Manager and Lead Estimator
-
($4.7 MM, 4 months) – 2021
-
Demolition, Fabrication and installation of ducting and structural steel for the Breaker Building, E House
-
Stainless steel, galvanized, round and square ducting, insulation. – up to 10’ in diameter ducting
-
Outage work working on one breaker at a time while the other 2 are in operation
-
High work – elevations as high as 150’ using rappel crew for outside wall work.
-
Removal and replacement, startup and commissioning of air handling units including E&I, controls and air balancing
Iberdrola Riser Upgrades Phase 1&2
-
Sr. Project Manager and Lead Estimator
-
($1.5 MM, 4 months) – 2020-2021
-
Excavation of existing 16/20” pipeline risers. Purge, cold cuts and demo of existing
-
Earthworks, line locates, piling, HDPE
-
CSA Z662 pipeline fabrication, install, outage work tie ins to plant
-
Involvement early in the project and worked with owner to optimize the workfronts and minimize downtime
​
CNRL Albian CST3 Pumphouse (300-BX-301)
-
Sr. Project Manager and Lead Estimator
-
($2.5 MM, 4 months) - 2020
-
2 – 4000 Hp Slurry Pumps – Install, epoxy grouting, alignments and pipe strains
-
Large bore 28” , internally coated pipe including field measure
-
59 TNE structural fabrication and install. 300 LM piping
-
HDPE Underground Glandwater and Drain Lines
-
EHT and Insulation
-
Outage and tie ins