top of page

Pump Stations & Compressor Stations

Sour Pump Station

  • Zero lost time incidents

  • On time and budget, working within the schedule to get the job done fast and safe.

  • Setting & installation of major equipment (tanks, package vessels)

  • Setting & Installation of building and pipe rack modules and interconnecting piping

  • quality control and turnover

  • commissioning of lines not completed by a previous contractor

  • Fabricate and install 50 tonnes of structural steel, 20,000 diameter inches.

  • Cut & cap

  • Shop Responsibilities

  • Electrical & Insulation                         

Pump Stations

  • Zero lost time injuries 

  • Projects often delivered ahead of schedule 

  • On budget

  • One of our Pump Stations we built was in a largely populated Aboriginal area. In which we Maintained a 25% aboriginal involvement, indenturing 3 new apprentices and mentor-ships.

  • Install of structural steel

  • Fabrication 

  • Full on site, system hydro-test

CNRL Albian 

CNRL Albian EDP Pond Piping System 

  • Sr. Project Manager and Lead Estimator

  • ($2.5 MM, 2 months) - 2022

  • Demo (20”), Fabrication and installation of piping (8” preinsulated) and structural steel for Inpit Tailings pond for ongoing production at MRM (including earthworks, HDPE fusing, CS welding, and testing).

CNRL Albian 14A Pumphouse (350-BX-101) 

  • Sr. Project Manager and Lead Estimator

  • ($2.5 MM, 4 months) - 2022

  • 2 – 4000 Hp Slurry Pumps – Install, epoxy grouting, alignments and pipe strains

  • Large bore 28” , internally coated pipe including field measure

  • 59 TNE structural fabrication and install. 300 LM piping

  • HDPE Underground Glandwater and Drain Lines

  • EHT and Insulation

  • Outage and tie ins

CNRL Albian HVAC Upgrades 

  • Sr. Project Manager and Lead Estimator

  • ($4.7 MM, 4 months) – 2021

  • Demolition, Fabrication and installation of ducting and structural steel for the Breaker Building, E House

  • Stainless steel, galvanized, round and square ducting, insulation. – up to 10’ in diameter ducting

  • Outage work working on one breaker at a time while the other 2 are in operation

  • High work – elevations as high as 150’ using rappel crew for outside wall work.

  • Removal and replacement, startup and commissioning of air handling units including E&I, controls and air balancing

Iberdrola Riser Upgrades Phase 1&2 

  • Sr. Project Manager and Lead Estimator

  • ($1.5 MM, 4 months) – 2020-2021

  • Excavation of existing 16/20” pipeline risers. Purge, cold cuts and demo of existing

  • Earthworks, line locates, piling, HDPE

  • CSA Z662 pipeline fabrication, install, outage work tie ins to plant

  • Involvement early in the project and worked with owner to optimize the workfronts and minimize downtime

CNRL Albian CST3 Pumphouse (300-BX-301)

  • Sr. Project Manager and Lead Estimator

  • ($2.5 MM, 4 months) - 2020

  • 2 – 4000 Hp Slurry Pumps – Install, epoxy grouting, alignments and pipe strains

  • Large bore 28” , internally coated pipe including field measure

  • 59 TNE structural fabrication and install. 300 LM piping

  • HDPE Underground Glandwater and Drain Lines

  • EHT and Insulation

  • Outage and tie ins

bottom of page