top of page

Pump Stations & Compressor Stations

Sour Pump Station

  • Zero lost time incidents

  • On time and budget, working within the schedule to get the job done fast and safe.

  • Setting & installation of major equipment (tanks, package vessels)

  • Setting & Installation of building and pipe rack modules and interconnecting piping

  • quality control and turnover

  • commissioning of lines not completed by a previous contractor

  • Fabricate and install 50 tonnes of structural steel, 20,000 diameter inches.

  • Cut & cap

  • Shop Responsibilities

  • Electrical & Insulation                         

Pump Stations

  • Zero lost time injuries 

  • Projects often delivered ahead of schedule 

  • On budget

  • One of our Pump Stations we built was in a largely populated Aboriginal area. In which we Maintained a 25% aboriginal involvement, indenturing 3 new apprentices and mentor-ships.

  • Install of structural steel

  • Fabrication 

  • Full on site, system hydro-test

CNRL Albian 

CNRL Albian EDP Pond Piping System 

  • Sr. Project Manager and Lead Estimator

  • ($2.5 MM, 2 months) - 2022

  • Demo (20”), Fabrication and installation of piping (8” preinsulated) and structural steel for Inpit Tailings pond for ongoing production at MRM (including earthworks, HDPE fusing, CS welding, and testing).

​

CNRL Albian 14A Pumphouse (350-BX-101) 

  • Sr. Project Manager and Lead Estimator

  • ($2.5 MM, 4 months) - 2022

  • 2 – 4000 Hp Slurry Pumps – Install, epoxy grouting, alignments and pipe strains

  • Large bore 28” , internally coated pipe including field measure

  • 59 TNE structural fabrication and install. 300 LM piping

  • HDPE Underground Glandwater and Drain Lines

  • EHT and Insulation

  • Outage and tie ins

​

CNRL Albian HVAC Upgrades 

  • Sr. Project Manager and Lead Estimator

  • ($4.7 MM, 4 months) – 2021

  • Demolition, Fabrication and installation of ducting and structural steel for the Breaker Building, E House

  • Stainless steel, galvanized, round and square ducting, insulation. – up to 10’ in diameter ducting

  • Outage work working on one breaker at a time while the other 2 are in operation

  • High work – elevations as high as 150’ using rappel crew for outside wall work.

  • Removal and replacement, startup and commissioning of air handling units including E&I, controls and air balancing

Iberdrola Riser Upgrades Phase 1&2 

  • Sr. Project Manager and Lead Estimator

  • ($1.5 MM, 4 months) – 2020-2021

  • Excavation of existing 16/20” pipeline risers. Purge, cold cuts and demo of existing

  • Earthworks, line locates, piling, HDPE

  • CSA Z662 pipeline fabrication, install, outage work tie ins to plant

  • Involvement early in the project and worked with owner to optimize the workfronts and minimize downtime

​

CNRL Albian CST3 Pumphouse (300-BX-301)

  • Sr. Project Manager and Lead Estimator

  • ($2.5 MM, 4 months) - 2020

  • 2 – 4000 Hp Slurry Pumps – Install, epoxy grouting, alignments and pipe strains

  • Large bore 28” , internally coated pipe including field measure

  • 59 TNE structural fabrication and install. 300 LM piping

  • HDPE Underground Glandwater and Drain Lines

  • EHT and Insulation

  • Outage and tie ins

bottom of page