Pembina Resthaven
Field Mechanical Construction
-
Module fabrication
-
Equipment setting
-
Structural and piping installation
-
Hydro-test
-
3 week turnaround with day and night shift, including welded/ bolted tie ins, testing and install
Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed
Field Mechanical Construction
Module fabrication
Equipment setting
Structural and piping installation
Hydro-test
3 week turnaround with day and night shift, including welded/ bolted tie ins, testing and install