Stats
•Zero lost time incidents
•Peak man power of 250 directs & indirect labour
•$19 MM CAD in total budget executed
•10,000 bbl/day plant
Field Mechanical Construction
•2.5km flow line installation
•6 km of HDPE underground pipe line with tie ins
•8 well pair buildings and interconnecting modules
•4,455 LM pipe install
•4,000 diameter inches welded
•224 tonnes of structural steel
•31 equipment and 15 modules installed

SemCams
Waipiti
Stats
-
Zero lost time injuries
-
Peak manpower - 163 craft labor & indirects
-
Project delivered ahead of schedule and under budget
Field Mechanical Construction
-
2,800 piles cut and capped
-
350 tonnes of field platforms & misc. structural steel
-
3 shop packages
-
Assisted with offload and setting of 151 pieces including towers, building and pipe racks
Shop Responsibilities
-
79,000 piping fabrication diameter inches
-
Structural Fabrication of supports and platforms (345 tonnes)
-
200,000 man hours