Sunshine
West Ells SAGD
Stats
-
Zero lost time incidents
-
Peak man power of 250 directs & indirect labour
-
Project completed on budget
-
10,000 bbl/day plant
Field Mechanical Construction
-
2.5km flow line installation
-
6 km of HDPE underground pipe line with tie ins
-
8 well pair buildings and interconnecting modules
-
4,455 LM pipe install
-
4,000 diameter inches welded
-
224 tonnes of structural steel
-
31 equipment and 15 modules installed